Cross Record

R_89

Changes to the latest version will be highlighted

View the validation rules glossary of terms

Name R_89
Version 1
Status Changed
Category Cross Record
Severity Error
Error message

The Learning actual end date for the latest programme aim must not be before the Learning actual end date of the latest component aim (not including English and maths)

Intent

This rule ensures that the programme aim is not closed with an actual end date if one of the component aims are still open, this does not include English and Maths.

Guidance

Check that the actual end date has not been added in error on the Programme aim, if the learner has completed the actual end date will need to be added onto the programme aim that matches the latest component.

Description

Where the Learning actual end date has been returned for the programme aim, it must not be before the Learning actual end date of the latest aim within that programme.

Detailed error condition
Detailed description

Where the Learning actual end date has been returned ( LearningDelivery.LearnActEndDate is known) for the programme aim ( LearningDelivery.AimType = 1), it must not be before the Learning actual end date of the latest aim within that programme.

(error where the latest programme aim LearnActEndDate is < latest component LearnActEndDate (AimType = 3)
with the same combination of ProgType and StdCode (where applicable))

(This rule is not triggered for English and maths component aims (
AimType = 3, and (LearnAimRef = LARS_LearnAimRef, and LARS_BasicSkillsType = 01, 11, 13, 20, 23, 24, 29, 31, 02, 12, 14, 19, 21, 25, 30, 32, 33, 34, 35)

Flow chart R89

Open flow chart in a new window

Flow chart details

Flowchart for 'R89' rule

1. Has the actual end date been recorded on the programme aim?

  • If 'No' then the rule is not triggered

  • If 'Yes' then:

2. Is there an open component aim as part of the programme?

  • If 'No' then the rule is not triggered

  • If 'Yes' then:

3. Is this an English or Maths learning aim?

  • If 'Yes' then the rule is not triggered

  • If 'No' then the rule is triggered

Change summary

Version 1

The framework and pathway code has been removed

Status summary

Current SLD severity

Error

Current FIS severity

Error

Is this rule in FIS?

Yes

Field values

LearningDelivery.ProgType

LearningDelivery.AimType

LearningDelivery.StdCode

AppFinRecord.AFinDate

AppFinRecord.AFinCode

LearningDelivery.LearnActEndDate

Need help understanding some of these terms?

View the validation rules glossary of terms