| Error message |
The Learning actual end date must not be returned for this Completion status |
| Intent |
To ensure that, where a Learning actual end date is returned, the correct Completion status code is used |
| Guidance |
Ensure that, where a Learning actual end date is returned, the Completion status is not code 1 (the learner is continuing or intending to continue the learning activities leading to the learning aim) |
| Description |
If the Learning actual end date is returned, then the Completion status must not be 'the learner is continuing or intending to continue the learning activities leading to the learning aim' |
| Detailed description |
If the Learning actual end date is returned (
LearningDelivery.LearnActEndDate
is known), then the Completion status must not be 'the learner is continuing or intending to continue the learning activities leading to the learning aim' |
|---|---|
| Exclusions |
This rule is not triggered by apprenticeship standard programmes ( LearningDelivery.AimType = 1 and LearningDelivery.FundModel = 36 or 99 and LearningDelivery.ProgType = 25) |
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for 'CompStatus_02' rule 1. Is an aim an apprenticeship programme?
2. Is the Learning actual end date returned?
3. Is the Completion status code 1?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
Need help understanding some of these terms?
View the validation rules glossary of terms