LearnAimRef_150
Changes to the latest version will be highlighted
View the validation rules glossary of terms
| Name | LearnAimRef_150 |
|---|---|
| Version | 1 |
| Status | New |
| Category | Learning delivery |
| Severity | Error |
| Error message |
The Learning aim reference is not valid in the LARS database for this Funding model and this Learning start date |
| Intent |
To ensure that only aims valid for Tailored learning provision are recorded |
| Guidance |
Ensure that, for new starts on or after 1 August 2024, that are Tailored Learning funded, then the learning aim start date must not be before the validity start date or be after the last date for new starts for the corresponding validity category in the Validity table in the LARS database, as shown through the FALA service |
| Description |
For new starts on or after 1 August 2024 and are Tailored Learning funded then the learning aim start date must not be before the validity start date or be after the last date for new starts (unless the restart indicator is present) for the corresponding validity category in the Validity table in the LARS database |
| Detailed description |
For new starts on or after 1 August 2024 and are Tailored Learning funded then the learning aim start date must not be before the validity start date or be after the last date for new starts (unless the restart indicator is present) for the corresponding validity category in the Validity table in the LARS database. (error where LearningDelivery.LearnActEndDate >= 2024-08-01 and LearningDelivery.FundModel = 11 and LearningDelivery.LearnStartDate < LARS_StartDate in the LARS Validity table or ( LearningDelivery.LearnStartDate > LARS_LastNewStartDate in the LARS_Validity table and LearningDeliveryFAM.LearnDelFamType = RES does not exist)) where ( LearningDelivery.LearnAimRef = LARS_LearnAimRef and LARS_ValidityCategory = Tailored_Learning) |
|---|---|
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for 'LearnAimRef_150' rule 1. Is the aim a Restart?
2. Is the aim start date on or after 1 August 2024?
3. Is the aim part of Tailored learning provision?
4. Is the learning aim start date before the validity start date or after the last date for new starts for the corresponding validity category in the Validity table in the LARS database?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
Need help understanding some of these terms?
View the validation rules glossary of terms