AchDate_11
Changes to the latest version will be highlighted
View the validation rules glossary of terms
| Name | AchDate_11 |
|---|---|
| Version | 1 |
| Status | Active |
| Category | Learning delivery |
| Severity | Error |
| Error message |
The Achievement date must be 7 days after the Learning actual end date |
| Intent |
To ensure that the Achievement date is recorded correctly for apprenticeship standard programmes |
| Guidance |
Ensure that, where the Achievement date is returned for an apprenticeship standard programme that ended on or after 1 August 2019, the Achievement date is at least 7 days after the Learning actual end date |
| Description |
For programme aims that are funded via apprenticeship standards that ended on or after 1 August 2019, the Achievement date must be at least 7 days after the Learning actual end date |
| Detailed description |
For programme aims (
LearningDelivery.AimType
= 1) that are funded via apprenticeship standards (
LearningDelivery.FundModel
= 36 and
LearningDelivery.ProgType
= 25) that ended on or after 1 August 2019 (
LearningDelivery.LearnActEndDate
=> 2019-08-01), the Achievement date (
LearningDelivery.AchDate
) must be at least 7 days after the Learning actual end date |
|---|---|
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for 'AchDate_11' rule 1. Is the aim an Apprenticeship standard programme?
2 . Is the Learning actual end date on or after 1 August 2019?
3. Is the aim Achievement date returned?
4. Is the Achievement date at least 7 days after the Learning actual end date?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
Need help understanding some of these terms?
View the validation rules glossary of terms