UKPRN_16
Changes to the latest version will be highlighted
View the validation rules glossary of terms
| Name | UKPRN_16 |
|---|---|
| Version | 1 |
| Status | Active |
| Category | Learner |
| Severity | Error |
| Error message |
This learning aim cannot be started after the Stop New Starts date for this funding relationship |
| Intent |
To ensure that there are no new starts under the delivery contract once a 'Stop New Starts' order has been placed on it. |
| Guidance |
Where a 'Stop New Starts' order has been placed on the contract for delivery, no new starts can be returned until this order has been removed from the contract. |
| Description |
If the learning aim is identified as procured non levy (ACT = 2 and FM = 36) there must be a funding relationship in FCT for this UKPRN, but the aim cannot be started on or after the Stop New Starts date of the latest contract start date. |
| Detailed description |
If the learning aim is identified as procured non levy (
LearningDelivery.LearnDelFAMType
= ACT and
LearningDelivery.LearnDelFAMCode
= 2) and (
LearningDelivery.AimType
= 1) and (
LearningDelivery.FundModel
= 36) there must be a funding relationship in FCT for this UKPRN (
LearningProvider.UKPRN
= ContractAllocation.DeliveryUKPRN and ContractAllocation.FundingStreamPeriodCode = 16-18NLAP2018, ANLAP2018), it cannot be started on or after the Stop New Starts date of the latest contract start date in FCT (ContractAllocation.StartDate) |
|---|---|
| Exclusions |
This rule is not triggered by Restarts ( LearningDelivery.LearnDelFAMType = RES) |
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for 'UKPRN_16' rule 1. Is the aim a Restart?
2. Is the programme aim part of a procured non-levy apprenticeship (ACT = 2)?
3. Is there a 'Stop new starts' instruction in FCT for the UKPRN?
4. Is the programme start date after the 'Stop new starts' instruction?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
N/A |
| Is this rule in FIS? |
No |
| Field values |
LearningDelivery.LearnStartDate LearningDeliveryFAM.LearnDelFAMType |
Need help understanding some of these terms?
View the validation rules glossary of terms