PHours_03
Changes to the latest version will be highlighted
View the validation rules glossary of terms
| Name | PHours_03 |
|---|---|
| Version | 1 |
| Status | Active |
| Category | Learning delivery |
| Severity | Error |
| Error message |
Planned hours must be returned for this funding model |
| Intent |
This rule ensures that T level programmes that start after August 2020 have the Phours field recorded |
| Guidance |
Check the learners start date for the T level programme and then update the Phours field accordingly |
| Description |
For starts on or after 1 August 2020, programme aim Planned hours must be returned for T Level programmes |
| Detailed description |
For starts on or after 1 August 2020, programme aims ( LearningDelivery.AimType = 1) ( LearningDelivery.LearnStartDate >= 2020-08-01), Planned hours must be returned for T Level programmes ( LearningDelivery.FundModel 25 and LearningDelivery.ProgType 31) (error where LearningDelivery.PHours is unknown) |
|---|---|
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for ' PHours_03 ' rule 1. Has the learner been recorded on a T level Programme?
2. Is the start date after the 1st of August 2020?
3. Has the Phours field been returned on the programme aim?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
Need help understanding some of these terms?
View the validation rules glossary of terms