| Error message |
Achievement date must only be returned on the programme aim |
| Intent |
This rule ensures the achievement date is recorded on the programme aim only. |
| Guidance |
Check the achievement date is recorded on the programme aim, the aim that is recorded with learning aim reference ZPROG001. |
| Description |
If returned, the Achievement date must be returned on the programme aim. |
| Detailed description |
If returned, the Achievement date must be returned on the programme aim. |
|---|---|
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for AchDate_14 rule: 1. Is Achievement Date returned?
2. Is the achievement date recorded on the programme aim?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
Need help understanding some of these terms?
View the validation rules glossary of terms