| Error message |
The Original learning start date must not be on or after the Learning start date |
| Intent |
This rule ensures that the original learning start date is before the recorded start date of the learning aim in the ILR. |
| Guidance |
Check the learning start date and the original start date is correct in the ILR and adjust accordingly. |
| Description |
If the Original learning start date is returned then it must be before the Learning start date |
| Detailed description |
If the Original learning start date is returned (LearningDelivery.OrigLearnStartDate is known), then it must be before the Learning start date (error where LearningDelivery.OrigLearnStartDate >= LearningDelivery.LearnStartDate) |
|---|---|
| Flow chart |
Open flow chart in a new window Flow chart detailsFlowchart for ' OrigLearnStartDate_02 ' rule 1. Is the original learning start date recorded before the learning start date in the ILR?
|
Change summary
Status summary
| Current SLD severity |
Error |
|---|---|
| Current FIS severity |
Error |
| Is this rule in FIS? |
Yes |
| Field values |
LearningDelivery.LearnStartDate |
Need help understanding some of these terms?
View the validation rules glossary of terms