Planned employability, enrichment and pastoral hours: Field
Definition
Total planned employability, enrichment and pastoral activity for the teaching year.
Reason Required
To enable 16-19 (excluding Apprenticeships) funding for learners. To measure the number of full-time and part-time learners in FE.
Schema Definitions
- XML Entity Name
- PlanEEPHours
- Field Length
- 4
- Data type
- xs:int
- Minimum occurrences
- 0
- Maximum occurrences
- 1
- Part of
- Learner
Collection Requirements
- 16-19 excluding Apprenticeships (FundModel 25)
- T Level Transition Programme (FundModel 25, ProgType 30)
Valid Entries
Must contain a value in the range 0 to 9999
Notes
-
The Planned employability, enrichment and pastoral hours must be recorded to the nearest whole hour.
-
This field should be completed at the start of the programme with the total planned timetabled employability, enrichment and pastoral hours for the learner for the teaching year.
-
This field must be updated at the start of each teaching year.
-
Include in this field all planned, timetabled hours included in the study programme that are not included in the Planned learning hours field. The total of both hours fields is used to determine the full or part-time funding rate for the learner. Further information can be found in the funding documentation.
-
This field must be finalised and confirmed as correct within the funding qualifying start period as defined in the funding documentation. By the end of the qualifying period it is important to ensure that the planned hours reflect, as accurately as possible, the timetabled activity the learner is planning to undertake for the duration of the teaching year.
-